Bathroom renovation is one of the topics that homeowners are most curious about. The question "How long will it take?" directly affects the project's success. With data from our 50+ bathroom renovation projects in Edremit, we offer you a realistic duration planning.
Bathroom Renovation Duration Factors
1. Project Scope
Small Renovation (6-8m²):
- Partial renovation: 7-10 days
- Complete renovation: 12-15 days
Medium Scale Renovation (8-12m²):
- Partial renovation: 10-14 days
- Complete renovation: 15-20 days
Large Renovation (12m²+):
- Partial renovation: 14-18 days
- Complete renovation: 20-25 days
2. Special Factors for Edremit Region
Climate Conditions:
- Drying times may be longer due to high humidity
- Working hours may be shortened during hot summer months
- Heating requirements in winter months may require additional time
Material Supply:
- Quick supply from local suppliers
- Additional 1-2 days for materials from Istanbul
- Additional 3-5 days for special orders
Detailed Duration Planning
Week 1: Preparation and Demolition
Days 1-2: Planning and Preparation
- Photographing current condition
- Material control
- Protection measures
Days 3-4: Demolition Work
- Removing old tiles
- Plumbing inspection
- New plumbing planning
Days 5-7: Plumbing Work
- Water plumbing renewal
- Electrical installation
- Ventilation system
Week 2: Main Work
Days 8-10: Plastering and Correction
- Wall corrections
- Plastering work
- Water insulation
Days 11-14: Tile Installation
- Floor tiles
- Wall tiles
- Grouting work
Week 3: Installation and Details
Days 15-17: Sanitary Installation
- Toilet installation
- Sink installation
- Shower cabin/Bathtub
Days 18-20: Electrical and Accessories
- Mirror installation
- Lighting
- Accessory installations
Day 21: Cleaning and Inspection
- Final cleaning
- Quality control
- Customer handover
Speed-Up Tips
- Prepare Materials in Advance: Having all materials ready before project start saves 3-5 days
- Speed Up Decision Making Process: Make design decisions in advance
- Work with a Single Company: Avoid coordination issues
- Prefer Simple Designs: Complex details extend duration
Yamanlar Build Duration Guarantee
With our experience in Edremit:
- Duration Guarantee: Commitment to complete within specified time
- Daily Reporting: Regular updates on project status
- Flexible Working: Flexible scheduling for emergencies
- Quality Focused: We don't compromise quality for speed
Frequently Asked Questions
Q: Does weather affect duration?
A: Yes, especially in humid weather, drying times may be longer. In this case, 2-3 days additional time is planned.
Q: What happens if there's material delay?
A: Thanks to our local supplier network, material delays occur at a rate of only 5%. If they occur, we offer alternative solutions.
Q: Which months are completed fastest?
A: April-May and September-October are the most suitable periods for ideal durations.
Contact us for detailed duration planning and free survey for your bathroom renovation project!